Realitos Solar SLF
150.49 MW generation in Duval, TX · In queue since September 2023 · Proposed COD December 2028
150.49 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-15
The Realitos Solar SLF project is a proposed solar generation facility with a total capacity of 150.49 MW. Located in Duval County, Texas, the project is being developed by Mesquite Creek LLC. It is currently listed as active in the ERCOT interconnection queue under queue ID ERCOT-26INR0196, with an interconnection queue entry date of September 7, 2023.
The proposed commercial operation date for the Realitos Solar SLF project is December 15, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is the Bruni (#8297) _x0013_ Crestonio (#8695) 138 kV line, managed by AEP.
Generated from interconnection queue and public data sources
State
TX
County
Duval
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Mesquite Creek LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Bruni (#8297) _x0013_ Crestonio (#8695) 138 kV line; AEP
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Realitos Solar SLF