Fort Chadbourne Cattle BESS
50.23 MW storage in Coke, TX · In queue since August 2023 · Proposed COD June 2027
50.23 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-29
The Fort Chadbourne Cattle BESS is a proposed 50.23 MW battery storage project located in Coke County, Texas. Developed by Fort Chadbourne BESS, the project consists of 50.23 MW of battery capacity. It is currently in the ERCOT interconnection queue as entry ERCOT-26INR0218, with a queue entry date of August 21, 2023.
The project's proposed commercial operation date is June 29, 2027, and its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the AEP Fort Chadbourne 138 kV substation (#6324). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Coke
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Fort Chadbourne BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
AEP Fort Chadbourne 138 kv substation (#6324)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Fort Chadbourne Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Fort Chadbourne Cattle BESS