Santa Monica Solar (ERCOT-26INR0228) — Project Summary

Queue ID
ERCOT-26INR0228
Capacity
105.85 MW
Technology
Solar
Status
active
Location
Navarro, TX
Region
ERCOT
Developer
Karol Solar IV
IA Status
Facility Study

Santa Monica Solar

ERCOT-26INR0228BetaActiveSolarERCOTLBNL + Live

105.85 MW generation in Navarro, TX · In queue since September 2023 · Proposed COD September 2028

105.85 MW

Capacity

1

Components

Solar

2y 8m

In Queue

Facility Study

IA Status

COD target: 2028

Status
as of 9y 7m ago
Latest milestonesite selectionENR · 2016-10-26
Interconnection

Total Duration

5 years

Facilities Study50%
Queue EntrySep 7, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-09-20

About

The Santa Monica Solar project is a proposed 105.85 MW solar generation facility in Navarro County, Texas. The project, developed by Karol Solar IV, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0228, with a queue entry date of September 7, 2023. The proposed commercial operation date is September 20, 2028, and the interconnection agreement status is currently in the Facility Study phase.

The Santa Monica Solar project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Navarro

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Karol Solar IV

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345 KV 68091 NAVARRO - 3381 BIGBRNW_5 Ckt 2

Data Source

LBNL + Live

DeveloperSolarReserve LLCENR · 2016-10-26
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Navarro Switching Station

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Santa Monica Solar