Titus Sienta Solar
501.93 MW generation in Pecos, TX · In queue since October 2023 · Proposed COD June 2028
501.93 MW
Capacity
1
Components
Solar
2y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
The Titus Sienta Solar project is a proposed 501.93 MW solar generation facility located in Pecos County, Texas. The project, developed by Sol Sienta Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0230, with a queue entry date of October 13, 2023. The proposed commercial operation date is June 1, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Tap 138kV 1239 Coyanosa - 11238 Blair Lake Sub. The Titus Sienta Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Sol Sienta Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 1239 Coyanosa - 11238 Blair Lake Sub
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Coyanosa Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.