Cairos Solar (ERCOT-26INR0246) — Project Summary

Queue ID
ERCOT-26INR0246
Capacity
153.26 MW
Technology
Solar
Status
active
Location
Kinney, TX
Region
ERCOT
Developer
Cairos Solar, LLC
IA Status
Facility Study

Cairos Solar

ERCOT-26INR0246BetaActiveSolarERCOTLBNL + Live

153.26 MW generation in Kinney, TX · In queue since October 2023 · Proposed COD December 2026

153.26 MW

Capacity

1

Components

Solar

2y 7m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

3y 2m

Facilities Study50%
Queue EntryOct 4, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

About

Cairos Solar, a proposed solar generation project in Kinney County, Texas, is being developed by Cairos Solar, LLC. The project has a total capacity of 153.26 MW, consisting entirely of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-26INR0246, with a queue entry date of October 4, 2023, and a proposed commercial operation date of December 31, 2026. The project's interconnection status is currently in the Facility Study phase.

The point of interconnection for Cairos Solar is the ODLAW SWITCH (#7425). The project has been mentioned in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Kinney

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Cairos Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

ODLAW SWITCH (#7425)

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.