Cairos Solar
153.26 MW generation in Kinney, TX · In queue since October 2023 · Proposed COD December 2026
153.26 MW
Capacity
1
Components
Solar
2y 7m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
Cairos Solar, a proposed solar generation project in Kinney County, Texas, is being developed by Cairos Solar, LLC. The project has a total capacity of 153.26 MW, consisting entirely of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-26INR0246, with a queue entry date of October 4, 2023, and a proposed commercial operation date of December 31, 2026. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection for Cairos Solar is the ODLAW SWITCH (#7425). The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Kinney
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cairos Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
ODLAW SWITCH (#7425)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.