Goldfinch Storage
100.44 MW storage in Van Zandt, TX · In queue since October 2023 · Proposed COD March 2028
100.44 MW
Capacity
1
Components
Battery
2y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-18
Goldfinch Storage is a proposed 100.44 MW battery storage project located in Van Zandt County, Texas. The development project, sponsored by BT DJ4M Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0254, with a queue entry date of October 4, 2023. The proposed commercial operation date is March 18, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is listed as Tap Connection Bus 2485 Poetry Switch _x0013_ 3223 Shamburger Switch.
Generated from interconnection queue and public data sources
State
TX
County
Van Zandt
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT DJ4M Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Connection Bus 2485 Poetry Switch _x0013_ 3223 Shamburger Switch
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Goldfinch Storage