Running Iron Solar (ERCOT-26INR0258) — Project Summary

Queue ID
ERCOT-26INR0258
Capacity
204.74 MW
Technology
Solar
Status
active
Location
Matagorda, TX
Region
ERCOT
Developer
Running Iron Solar, LLC
IA Status
Facility Study

Running Iron Solar

ERCOT-26INR0258BetaActiveSolarERCOTLBNL + Live

204.74 MW generation in Matagorda, TX · In queue since October 2023 · Proposed COD October 2028

204.74 MW

Capacity

1

Components

Solar

2y 7m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

5 years

Facilities Study50%
Queue EntryOct 25, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-16

About

Running Iron Solar is a proposed solar generation project located in Matagorda County, Texas, with a total capacity of 204.74 MW. The project, developed by Running Iron Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-26INR0258, with a queue entry date of October 25, 2023. The proposed commercial operation date is October 16, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.

The proposed project consists of 204.74 MW of solar photovoltaic generation. The point of interconnection is Tap 138kV Conoco 8138 - Black Cat 80124. The Running Iron Solar project has been mentioned in recent news coverage related to the energy industry and grid development.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Matagorda

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Running Iron Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138kV Conoco 8138 - Black Cat 80124

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Running Iron Solar