Malala Storage
205.5 MW storage in Dallas, TX · In queue since October 2023 · Proposed COD April 2028
205.5 MW
Capacity
1
Components
Battery
2y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-21
The Malala Storage project is a proposed 205.5 MW battery energy storage system in Dallas County, Texas. Developed by Malala Storage, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-26INR0274 on October 25, 2023. The proposed commercial operation date is April 21, 2028, and the project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Malala operating plant (EIA ID 67660). The interconnection point of contact is the 2434 Seagoville SW 138kV substation.
Generated from interconnection queue and public data sources
State
TX
County
Dallas
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Malala Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
2434 Seagoville SW 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- POI Substation
- Seagoville Substation