Firebird Solar
100.42 MW generation in Ector, TX · In queue since November 2023 · Proposed COD December 2026
100.42 MW
Capacity
1
Components
Solar
2y 6m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
Firebird Solar is a proposed 100.42 MW solar generation project located in Ector County, Texas. The developer is TX Firebird SB 6, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0279, with a queue entry date of November 14, 2023.
The proposed commercial operation date for Firebird Solar is December 31, 2026. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 138 kV 1099 SOUTHWESTERN PORTLAND TAP - 11281 OLSIN SWITCH.
Generated from interconnection queue and public data sources
State
TX
County
Ector
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
TX Firebird SB 6, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV 1099 SOUTHWESTERN PORTLAND TAP - 11281 OLSIN SWITCH
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.