SHAWNEE BOTTOM SOLAR
153 MW generation in Nacogdoches, TX · In queue since September 2023 · Proposed COD June 2026
153 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
2y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
The Shawnee Bottom Solar project is a proposed 153 MW solar generation facility in Nacogdoches County, Texas. Developed by Shawnee Bottom Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0281, with a queue entry date of September 22, 2023. The proposed commercial operation date is June 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 153 MW of solar photovoltaic generation. The point of interconnection is on the tap 138kV 3319 REDLAND_8 - 3120 NACOGDSE_8 transmission line. The Shawnee Bottom Solar project has been mentioned in recent news coverage related to the electric grid.
Generated from interconnection queue and public data sources
State
TX
County
Nacogdoches
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Shawnee Bottom Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 3319 REDLAND_8 - 3120 NACOGDSE_8
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26