Firebird BESS
100.42 MW storage in Ector, TX · In queue since November 2023 · Proposed COD August 2028
100.42 MW
Capacity
1
Components
Battery
2y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-28
The Firebird BESS project is a proposed 100.42 MW battery storage project located in Ector County, Texas. Developed by TX BESS 6, LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-26INR0287, with a queue entry date of November 14, 2023.
The proposed commercial operation date for the Firebird BESS project is August 28, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is the 138 kV 1099 SOUTHWESTERN PORTLAND TAP - 11281 OLSIN SWITCH.
Generated from interconnection queue and public data sources
State
TX
County
Ector
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
TX BESS 6, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV 1099 SOUTHWESTERN PORTLAND TAP - 11281 OLSIN SWITCH
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Firebird BESS