Wadsworth Storage Energy Center
200.8 MW storage in Matagorda, TX · In queue since October 2023 · Proposed COD June 2026
200.8 MW
Capacity
1
Components
Battery
2y 7m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
The Wadsworth Storage Energy Center is a proposed 200.8 MW battery storage project located in Matagorda County, Texas. Developed by Nova Clean Energy Real Estate, LLC, the project entered the ERCOT interconnection queue as ERCOT-26INR0289 on October 25, 2023, with a proposed commercial operation date of June 1, 2026. Its interconnection status is currently in the Facility Study phase.
The project consists of 200.8 MW of battery storage capacity. The Wadsworth Storage Energy Center has been the subject of recent news coverage, with 12 articles primarily focused on regulatory aspects.
Generated from interconnection queue and public data sources
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Nova Clean Energy Real Estate, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8115 Wadsworth Substation 138 kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Wadsworth Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26