Carolina Storage Young County
104.4 MW storage in Young, TX · In queue since February 2024 · Proposed COD August 2028
104.4 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
The Carolina Storage Young County project is a proposed 104.4 MW battery storage project located in Young County, Texas. The developer is CSE STORAGE, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0302, with a queue entry date of February 27, 2024. The proposed commercial operation date is August 1, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is at the TAP 138 KV BUS, creating a new bus between Murray (792) and Graham SES (1431).
Generated from interconnection queue and public data sources
State
TX
County
Young
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CSE STORAGE, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 138 KV BUS AND CREAT NEW BUS BETWEEN MURRAY (792) AND GRAHAM SES (1431) COUNTY : YOUNG
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Carolina Storage Young County