Solace Storage (ERCOT-26INR0309) — Project Summary

Queue ID
ERCOT-26INR0309
Capacity
321.02 MW
Technology
Battery
Status
active
Location
Haskell, TX
Region
ERCOT
Developer
IP Quantum BESS, LLC
IA Status
Facility Study

Solace Storage

ERCOT-26INR0309BetaActiveBatteryERCOTLBNL + Live

321.02 MW storage in Haskell, TX · In queue since March 2024 · Proposed COD June 2026

321.02 MW

Capacity

1

Components

Battery

2y 2m

In Queue

Facility Study

IA Status

COD target: 2026

Status
as of 2 years ago
Latest activitypartnershipEcoWatch · 2024-05-31
Interconnection

Total Duration

2y 3m

Facilities Study50%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-01

About

The Solace Storage project is a proposed 321.02 MW battery energy storage system located in Haskell County, Texas. The project, developed by IP Quantum BESS, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0309, with a queue entry date of March 22, 2024. The proposed commercial operation date is June 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.

The proposed project will interconnect at the tap 345kV 1430 Graham - 1048 Tonkawas. Solace Storage has been the subject of recent news coverage, including reports related to industry developments and business deals.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Haskell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

IP Quantum BESS, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 1430 Graham - 1048 Tonkawas

Data Source

LBNL + Live

PartnerConsumers EnergyEcoWatch · 2024-05-31
CompanyEnvironmental Law & Policy CenterEcoWatch · 2024-05-31
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
GRSES_UNIT1
POI Substation
Graham Substation