Quantum Storage
321.06 MW storage in Haskell, TX · In queue since March 2024 · Proposed COD June 2026
321.06 MW
Capacity
1
Components
Battery
2y 2m
In Queue
IA Executed
IA Status
Signed Oct 2023
IA → COD
2y 8m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-06-01
The proposed Quantum Storage project is a 321.06 MW battery storage development in Haskell County, Texas. The project, developed by IP Quantum II BESS, LLC, is located within the ERCOT region and has interconnection queue ID ERCOT-26INR0310.
The project entered the ERCOT interconnection queue on March 22, 2024, with a proposed commercial operation date of June 1, 2026. The interconnection agreement for the project was executed on October 26, 2023. The point of interconnection is the 60089 Kilby Switching Station 345kV.
Generated from interconnection queue and public data sources
State
TX
County
Haskell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Quantum II BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60089 Kilby Switching Station 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.