Kobernat Solar (ERCOT-26INR0322) — Project Summary

Queue ID
ERCOT-26INR0322
Capacity
100.54 MW
Technology
Solar
Status
active
Location
Starr, TX
Region
ERCOT
Developer
BT Kobernat Solar, LLC
IA Status
Facility Study

Kobernat Solar

ERCOT-26INR0322BetaActiveSolarERCOTLBNL

100.54 MW generation in Starr, TX · In queue since February 2024 · Proposed COD December 2026

100.54 MW

Capacity

1

Components

Solar

2y 3m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

2y 10m

Facilities Study50%
Queue EntryFeb 2, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-30

About

Kobernat Solar is a proposed 100.54 MW solar generation project located in Starr County, Texas. The project, developed by BT Kobernat Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-26INR0322, with a queue entry date of February 2, 2024. The proposed commercial operation date is December 30, 2026.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is a direct connection to a new switching station on the AEP Texas Central owned Garza (Bus #8399) - Liston (Bus #8394) 138 kV line.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Starr

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BT Kobernat Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

A DIRECT CONNECTION TO A NEW SWITCHING STATION ON THE AEP TEXAS CENTRAL OWNED GARZA (BUS #8399) - LISTON (BUS #8394) 138 KV LINE

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Kobernat Solar