Leaning Tree BESS
256.1 MW storage in Throckmorton, TX · In queue since November 2023 · Proposed COD February 2027
256.1 MW
Capacity
1
Components
Battery
2y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-13
Leaning Tree BESS is a proposed 256.1 MW battery storage project in Throckmorton County, Texas. Developed by RamZ BESS, LLC, the project consists of 256.1 MW of battery capacity. It is listed in the ERCOT interconnection queue as entry ERCOT-26INR0326, with a queue entry date of November 30, 2023, and a proposed commercial operation date of February 13, 2027. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection is planned for the To Tap 345 kV Thomas Price Switch (Bus# 11523) to Clear Crossing (Bus# 60515) Line. The development has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Throckmorton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RamZ BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
To Tap 345 kV Thomas Price Switch (Bus# 11523) to Clear Crossing (Bus# 60515) Line
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Leaning Tree BESS