Yorktown BESS
150.49 MW storage in Dewitt, TX · In queue since October 2023 · Proposed COD December 2028
150.49 MW
Capacity
1
Components
Battery
2y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-16
The Yorktown BESS project is a proposed 150.49 MW battery storage project located in Dewitt County, Texas. Developed by Navitas Energy LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0328, with a queue entry date of October 25, 2023, and a proposed commercial operation date of December 16, 2028. The project's interconnection agreement status is currently in the Facility Study phase, and it is planned to connect to the LCRA Yorktown 138 kV point of interconnection.
The Yorktown BESS project has been mentioned in recent news coverage related to grid infrastructure.
Generated from interconnection queue and public data sources
State
TX
County
Dewitt
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Navitas Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
(#78575) LCRA Yorktown 138 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.