RUSH ESS (ERCOT-26INR0331) — Project Summary

Queue ID
ERCOT-26INR0331
Capacity
202.7 MW
Technology
Battery
Status
active
Location
Bexar, TX
Region
ERCOT
Developer
OCI Solar Power LLC
IA Status
Facility Study

RUSH ESS

ERCOT-26INR0331BetaActiveBatteryERCOTLBNL + Live

202.7 MW storage in Bexar, TX · In queue since November 2023 · Proposed COD July 2027

202.7 MW

Capacity

1

Components

Battery

2y 6m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

3y 8m

Facilities Study50%
Queue EntryNov 30, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-01

About

The RUSH ESS project is a proposed 202.7 MW battery storage project located in Bexar County, Texas. Developed by OCI Solar Power LLC, it is interconnected within the ERCOT region under queue ID ERCOT-26INR0331. The project entered the queue on November 30, 2023, and has a proposed commercial operation date of July 1, 2027. Its interconnection status is currently in the Facility Study phase.

The proposed project is linked to the existing Rush ESS operating plant (EIA ID 68361). Recent news coverage indicates interest in the project related to grid infrastructure.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Bexar

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

OCI Solar Power LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345 kV 5231 HOWARD_5 _x0013_ 5400 SPRUCE

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
CALAVER_JKS2
POI Substation
J. K. Spruce Switchyard

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about RUSH ESS