SOUTHERN SELECT ENERGY STORAGE (ERCOT-26INR0340) — Project Summary

Queue ID
ERCOT-26INR0340
Capacity
404.3 MW
Technology
Battery
Status
active
Location
Galveston, TX
Region
ERCOT
Developer
SOUTHERN SELECT ENERGY STORAGE LLC
IA Status
Facility Study

SOUTHERN SELECT ENERGY STORAGE

ERCOT-26INR0340BetaActiveBatteryERCOTLBNL + Live

404.3 MW storage in Galveston, TX · In queue since October 2023 · Proposed COD March 2027

404.3 MW

Capacity

1

Components

Battery

2y 7m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

3y 5m

Facilities Study50%
Queue EntryOct 25, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-03-31

About

The Southern Select Energy Storage project is a proposed 404.3 MW battery storage project located in Galveston County, Texas. The developer is Southern Select Energy Storage LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-26INR0340, with a queue entry date of October 25, 2023, and a proposed commercial operation date of March 31, 2027. The project's interconnection agreement status is currently in the Facility Study phase.

The Southern Select Energy Storage project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Galveston

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

SOUTHERN SELECT ENERGY STORAGE LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Bus Name: TNHEIGHTS_1 Bus Number: 38740

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.