Stinger Energy Storage
200.8 MW storage in Harris, TX · In queue since November 2023 · Proposed COD March 2028
200.8 MW
Capacity
1
Components
Battery
2y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
The Stinger Energy Storage project is a proposed 200.8 MW battery storage project located in Harris County, Texas. Developed by Stinger Energy Storage LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0343, with a queue entry date of November 14, 2023. The proposed commercial operation date is March 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the project is the Tap Atascocita 138kV Substation (Bus # 40130) - Lake Houston (Bus #40820).
Generated from interconnection queue and public data sources
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Stinger Energy Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Atascocita 138kV Substation (Bus # 40130) - Lake Houston (Bus #40820)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Atascocita Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Stinger Energy Storage