NET Power Demonstration plant (ERCOT-26INR0345) — Project Summary

Queue ID
ERCOT-26INR0345
Capacity
25.5 MW
Technology
Gas
Status
active
Location
Harris, TX
Region
ERCOT
Developer
NET Power LLC
IA Status
Facility Study

NET Power Demonstration plant

ERCOT-26INR0345BetaActiveGasERCOTLBNL + Live

25.5 MW generation in Harris, TX · In queue since December 2023 · Proposed COD August 2027

25.5 MW

Capacity

1

Components

Gas

2y 5m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection

Total Duration

3y 8m

Facilities Study50%
Queue EntryDec 20, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-08-21

About

The NET Power Demonstration plant is a proposed 25.5 MW gas-fired generation project located in Harris County, Texas. Developed by NET Power LLC, the project is interconnected within the Electric Reliability Council of Texas (ERCOT) region under queue ID ERCOT-26INR0345. The project entered the interconnection queue on December 20, 2023, and has a proposed commercial operation date of August 21, 2027. Its interconnection status is currently in the Facility Study phase.

The proposed project is linked to the existing NET Power La Porte Station operating plant (EIA ID 60910). Recent news coverage has discussed the development project.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Harris

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

NET Power LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

42360 Mirage POI 8 138kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
HIGH
Nearest Node (Estimated)
MIRAGE_G1
POI Substation
Mirage Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about NET Power Demonstration plant