NET Power Demonstration plant
25.5 MW generation in Harris, TX · In queue since December 2023 · Proposed COD August 2027
25.5 MW
Capacity
1
Components
Gas
2y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-21
The NET Power Demonstration plant is a proposed 25.5 MW gas-fired generation project located in Harris County, Texas. Developed by NET Power LLC, the project is interconnected within the Electric Reliability Council of Texas (ERCOT) region under queue ID ERCOT-26INR0345. The project entered the interconnection queue on December 20, 2023, and has a proposed commercial operation date of August 21, 2027. Its interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing NET Power La Porte Station operating plant (EIA ID 60910). Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
NET Power LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
42360 Mirage POI 8 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MIRAGE_G1
- POI Substation
- Mirage Substation