ARTIO ENERGY STORAGE
205.94 MW storage in Collin, TX · In queue since November 2023 · Proposed COD October 2028
205.94 MW
Capacity
1
Components
Battery
2y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
The Artio Energy Storage project is a proposed 205.94 MW battery storage project located in Collin County, Texas. Developed by Artio Energy Storage LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0349, with a queue entry date of November 14, 2023. The project's proposed commercial operation date is October 1, 2028, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project consists solely of battery storage, with a total capacity of 205.94 MW. The point of interconnection is the Farmersville 345kV Substation (PSSE BUS # 1685). The Artio Energy Storage project has appeared in recent news coverage regarding energy storage developments in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Collin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Artio Energy Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Farmersville 345kV Substation (PSSE BUS # 1685)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FRMR_BS2_RN1
- POI Substation
- Farmersville Substation