Jack County III _x0013_ 345 kV (TEF -Due Diligence)
660 MW generation in Jack, TX · In queue since November 2023 · Proposed COD July 2027
660 MW
Capacity
1
Components
Gas
2y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
The proposed Jack County III _x0013_ 345 kV (TEF -Due Diligence) project is a 660 MW natural gas generation facility in Jack County, Texas. The project, being developed by Jack County Power Development, LLC, is located within the ERCOT region. It entered the ERCOT interconnection queue as project ERCOT-26INR0351 on November 14, 2023, and has a proposed commercial operation date of July 1, 2027. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection is the JACK COUNTY 2 PLANT substation (station code JCKCNTY2, bus number 575). The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Jack
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Jack County Power Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Substation Name: JACK COUNTY 2 PLANT STATION CODE: JCKCNTY2 BUS NUMBER: 575
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Plant X Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.