Pleiades Storage
205.5 MW storage in Glasscock, TX · In queue since March 2024 · Proposed COD September 2028
205.5 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-22
Pleiades Storage, LLC is proposing a 205.5 MW battery storage project in Glasscock County, Texas. The project, identified as ERCOT-26INR0355 in the ERCOT interconnection queue, entered the queue on March 22, 2024, with a proposed commercial operation date of September 22, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 205.5 MW of battery storage. The point of interconnection is Tap 138kV Einstein 23852 - 10043 St. Lawrence. The project is listed as active in the ERCOT queue.
Generated from interconnection queue and public data sources
State
TX
County
Glasscock
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pleiades Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Einstein 23852 - 10043 St. Lawrence
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Pleiades Storage