Saluga Ranch Storage
105.98 MW storage in Dimmit, TX · In queue since February 2024 · Proposed COD August 2027
105.98 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-25
The Saluga Ranch Storage project is a proposed 105.98 MW battery energy storage system in Dimmit County, Texas. Developed by Saluga Ranch Energy, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0356, with a queue entry date of February 2, 2024. The proposed commercial operation date is August 25, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Asherton 8283 - Big wells 8613 -138 kV location. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Dimmit
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Saluga Ranch Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Asherton 8283 - Big wells 8613 -138 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.