Uva Creek Solar
302.16 MW generation in Borden, TX · In queue since February 2024 · Proposed COD August 2028
302.16 MW
Capacity
1
Components
Solar
2y 3m
In Queue
IA Executed
IA Status
Signed Oct 2024
Queue → IA
8 months
IA → COD
3y 10m
Total Duration
8 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-08-25
Uva Creek Solar is a proposed solar generation project with a total capacity of 302.16 MW, located in Borden County, Texas. The developer is Grape Creek Solar, LLC. The project is interconnected within the ERCOT region and is listed in the ERCOT interconnection queue as entry 26INR0359, with a queue entry date of February 27, 2024. The proposed commercial operation date is August 25, 2028. The Interconnection Agreement (IA) has been executed as of October 30, 2024.
The proposed project is linked to the existing Uva Creek Solar operating plant (EIA ID 68739). The point of interconnection is Tap 345 kV 59905 Faraday - 59900 Long Draw. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Borden
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Grape Creek Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 59905 Faraday - 59900 Long Draw
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Gail Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.