BLACK BEAR BESS
51.2 MW storage in Crockett, TX · In queue since December 2023 · Proposed COD June 2028
51.2 MW
Capacity
1
Components
Battery
2y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
The proposed BLACK BEAR BESS project is a 51.2 MW battery storage development in Crockett County, Texas. It is being developed by ESCONDIDO DRAW RESOURCES, LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-26INR0366, with an interconnection queue entry date of December 4, 2023.
The proposed commercial operation date for BLACK BEAR BESS is June 1, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is #6564 ILLN4A 138kV.
Generated from interconnection queue and public data sources
State
TX
County
Crockett
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ESCONDIDO DRAW RESOURCES, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#6564 ILLN4A 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about BLACK BEAR BESS