Centennial Solar
61.36 MW generation in Menard, TX · In queue since January 2024 · Proposed COD April 2028
61.36 MW
Capacity
1
Components
Solar
2y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-29
The Centennial Solar project is a proposed 61.36 MW solar generation facility in Menard County, Texas. The project, developed by Centennial AD 8 LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0372, with a queue entry date of January 3, 2024. The proposed commercial operation date is April 29, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 6364 YELLOW JACKET - 76390 FORT MASON. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Menard
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Centennial AD 8 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 6364 YELLOW JACKET - 76390 FORT MASON
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Centennial Solar