Cobra Clean Energy Center
100.4 MW storage in Brazoria, TX · In queue since February 2024 · Proposed COD October 2027
100.4 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-08
The Cobra Clean Energy Center is a proposed 100.4 MW battery storage project located in Brazoria County, Texas. Developed by Cobra Clean Energy Center LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0374, with a queue entry date of February 2, 2024.
The proposed commercial operation date for the Cobra Clean Energy Center is October 8, 2027. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is planned to be looped on circuit 04 between Mustang Bayou (#42960) and Hudson (#42100).
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cobra Clean Energy Center LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
looped on circuit 04 between Mustang Bayou (#42960) and Hudson (#42100)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.