Larimar Solar (ERCOT-26INR0378) — Project Summary

Queue ID
ERCOT-26INR0378
Capacity
150.91 MW
Technology
Solar
Status
active
Location
Bee, TX
Region
ERCOT
Developer
BT S7 Solar, LLC
IA Status
Facility Study

Larimar Solar

ERCOT-26INR0378BetaActiveSolarERCOTLBNL

150.91 MW generation in Bee, TX · In queue since January 2024 · Proposed COD December 2026

150.91 MW

Capacity

1

Components

Solar

2y 4m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

2y 11m

Facilities Study50%
Queue EntryJan 11, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-18

About

The Larimar Solar project is a proposed 150.91 MW solar generation facility in Bee County, Texas. The project, developed by BT S7 Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0378, with a queue entry date of January 11, 2024. The proposed commercial operation date is December 18, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.

The proposed project consists of 150.91 MW of solar photovoltaic generation. The point of interconnection is Tap 138 kV 8186 KENEDYSW4A _x0010_ 8590 TULETA4A. The Larimar Solar project has appeared in recent news coverage regarding renewable energy development in Texas.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Bee

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

BT S7 Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 138 kV 8186 KENEDYSW4A _x0010_ 8590 TULETA4A

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Larimar Solar