Pepper Solar Farm
120.69 MW generation in Mclennan, TX · In queue since February 2024 · Proposed COD September 2027
120.69 MW
Capacity
1
Components
Solar
2y 3m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-20
Pepper Solar Farm is a proposed solar generation project with a total capacity of 120.69 MW. The project, developed by Pepper Solar Farm LLC, is located in McLennan County, Texas, within the ERCOT region. It is listed in the ERCOT interconnection queue as entry 26INR0380, with a queue entry date of February 27, 2024, and a proposed commercial operation date of September 20, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Pepper Solar Farm operating plant (EIA ID 68359). Recent news coverage indicates activity related to the project, specifically in the area of deals.
Generated from interconnection queue and public data sources
State
TX
County
Mclennan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pepper Solar Farm LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3405 THOUSE__5 - 3406 ELM_MOTT_5
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
- POI Substation
- Elm Mott Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Pepper Solar Farm