Larimar Storage
100.91 MW storage in Bee, TX · In queue since January 2024 · Proposed COD December 2026
100.91 MW
Capacity
1
Components
Battery
2y 4m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-18
Larimar Storage is a proposed 100.91 MW battery storage project located in Bee County, Texas. The project, being developed by BT S7 Solar, LLC, is interconnected within the ERCOT region under queue ID ERCOT-26INR0383. The project entered the queue on January 11, 2024, and has a proposed commercial operation date of December 18, 2026. Its interconnection status is currently in the Facility Study phase.
The proposed project consists solely of battery storage, with a total capacity of 100.91 MW. The point of interconnection is a direct connection to a new switching station on the Kenedysw4A (Bus #8186) _x0010_ Tuleta4A (Bus #8590) 138 kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Bee
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BT S7 Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
A DIRECT CONNECTION TO A NEW SWITCHING STATION ON THE KENEDYSW4A (BUS #8186) _x0010_ TULETA4A (BUS #8590) 138 KV LINE
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Larimar Storage