Liatris Flexible Gas
204.71 MW generation in Brazoria, TX · In queue since March 2024 · Proposed COD February 2029
204.71 MW
Capacity
1
Components
Gas
2y 2m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-02-01
The Liatris Flexible Gas project is a proposed 204.71 MW gas-fired generation project located in Brazoria County, Texas. Developed by Stone Creek Peaker LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0408, with a queue entry date of March 22, 2024.
The proposed commercial operation date for the project is February 1, 2029. Its interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Stone Creek Peaker LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV (42980) Nash - (44010) WA Parish CKT02
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.