Twinwood Solar 1
358.06 MW generation in Waller, TX · In queue since March 2024 · Proposed COD October 2027
358.06 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-27
Twinwood Solar 1 is a proposed solar generation project located in Waller County, Texas, within the ERCOT region. The project, developed by Twinwood PV1, LLC, has a total capacity of 358.06 MW. It consists entirely of solar photovoltaic generation.
The project is listed in the ERCOT interconnection queue as entry ERCOT-26INR0425, with a queue entry date of March 22, 2024. The proposed commercial operation date is October 27, 2027. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 44750 FULSHR_S25_8 - 44860 TWINWD_S25_8.
Generated from interconnection queue and public data sources
State
TX
County
Waller
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Twinwood PV1, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 44750 FULSHR_S25_8 - 44860 TWINWD_S25_8
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.