BremRaek BESS
200.6 MW storage in Austin, TX · In queue since March 2024 · Proposed COD November 2027
200.6 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-14
The BremRaek BESS project is a proposed 200.6 MW battery storage project located in Austin County, Texas. The project, developed by BremRaek BESS, entered the ERCOT interconnection queue as entry ERCOT-26INR0427 on March 22, 2024. Its proposed commercial operation date is November 14, 2027. The project's interconnection status is currently in the Facility Study phase.
The project consists of 200.6 MW of battery storage capacity. The point of interconnection is the 7271 LCRA New Bremen 138 kV substation. The BremRaek BESS project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Austin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BremRaek BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7271 LCRA New Bremen 138 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- New Bremen Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about BremRaek BESS