Big Rooter West Solar SLF (ERCOT-26INR0431) — Project Summary

Queue ID
ERCOT-26INR0431
Capacity
403.42 MW
Technology
Solar
Status
active
Location
Robertson, TX
Region
ERCOT
Developer
Big Rooter West, LLC
IA Status
Facility Study

Big Rooter West Solar SLF

ERCOT-26INR0431BetaActiveSolarERCOTLBNL + Live

403.42 MW generation in Robertson, TX · In queue since March 2024 · Proposed COD May 2028

403.42 MW

Capacity

1

Components

Solar

2y 2m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

4y 2m

Facilities Study50%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-31

About

Big Rooter West Solar SLF is a proposed solar generation project located in Robertson County, Texas, with a total capacity of 403.42 MW. Developed by Big Rooter West, LLC, the project consists entirely of solar photovoltaic generation.

The project is currently in the ERCOT interconnection queue as entry ERCOT-26INR0431, with a queue entry date of March 22, 2024. Its proposed commercial operation date is May 31, 2028, and its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is listed as 39950# TNTNP_ONE_3 345 KV. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Robertson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Big Rooter West, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

39950# TNTNP_ONE_3 345 KV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.