Donna BESS (ERCOT-26INR0442) — Project Summary

Queue ID
ERCOT-26INR0442
Capacity
54.08 MW
Technology
Battery
Status
active
Location
Hidalgo, TX
Region
ERCOT
Developer
Donna Solar LLC
IA Status
Facility Study

Donna BESS

ERCOT-26INR0442BetaActiveBatteryERCOTLBNL + Live

54.08 MW storage in Hidalgo, TX · In queue since March 2024 · Proposed COD February 2029

54.08 MW

Capacity

1

Components

Battery

2y 2m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection

Total Duration

4y 11m

Facilities Study50%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-02-22

About

The Donna BESS project is a proposed 54.08 MW battery storage project located in Hidalgo County, Texas. The developer is Donna Solar LLC. It is interconnected within the ERCOT region under queue ID ERCOT-26INR0442, with a queue entry date of March 22, 2024, and a proposed commercial operation date of February 22, 2029. The project's interconnection status is currently in the Facility Study phase.

The Donna BESS project has been the subject of recent news coverage, with three articles focusing on industry trends and deals related to the project.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Hidalgo

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Donna Solar LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345 kV 80137 Stewart Road - 8383 North Edinburg

Data Source

LBNL + Live

DeveloperDSD RenewablesPOWER Magazine · 2023-10-05
TransactionPPAPOWER Magazine · 2023-10-05
OfftakerDollar TreePOWER Magazine · 2023-10-05
PPA structureCommunityPOWER Magazine · 2023-10-05
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
GKS_BESS_RN
POI Substation
Stewart Road Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about Donna BESS