Honey Mesquite Wind Farm
180.48 MW generation in Glasscock, TX · In queue since March 2024 · Proposed COD December 2026
180.48 MW
Capacity
1
Components
Wind
2y 2m
In Queue
IA Executed
IA Status
Signed Sep 2024
Queue → IA
6 months
IA → COD
2y 3m
Total Duration
6 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-12-15
The Honey Mesquite Wind Farm is a proposed wind generation project located in Glasscock County, Texas, within the ERCOT region. Developed by Honey Mesquite Wind Farm, LLC, the project has a total capacity of 180.48 MW, consisting entirely of wind generation. The project entered the ERCOT interconnection queue as queue ID ERCOT-26INR0447 on March 22, 2024, with a proposed commercial operation date of December 15, 2026.
The project's interconnection agreement (IA) has been executed as of September 16, 2024. The point of interconnection is the 59902 Sand Bluff 345kV substation. The Honey Mesquite Wind Farm has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Glasscock
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Honey Mesquite Wind Farm , LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59902 Sand Bluff 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Sand Bluff Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Honey Mesquite Wind Farm