Lightning Ridge Energy Storage
204.7 MW storage in Jack, TX · In queue since March 2024 · Proposed COD March 2028
204.7 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-21
Lightning Ridge Energy Storage is a proposed 204.7 MW battery storage project in Jack County, Texas. The project, developed by Lightning Ridge Storage LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0460, with a queue entry date of March 29, 2024. The proposed commercial operation date is March 21, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The Lightning Ridge Energy Storage project has been the subject of recent news coverage, with four articles appearing in industry and deals publications.
Generated from interconnection queue and public data sources
State
TX
County
Jack
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lightning Ridge Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap #1429 Jacksboro Substation 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Lightning Ridge Energy Storage