Ceres BESS
202.7 MW storage in Hunt, TX · In queue since October 2024 · Proposed COD November 2027
202.7 MW
Capacity
1
Components
Battery
1y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-30
The Ceres BESS project is a proposed 202.7 MW battery storage project located in Hunt County, Texas. Developed by Ceres BESS, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0464, with a queue entry date of October 29, 2024. The proposed commercial operation date is November 30, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138 kV 6883 QUINLAN NORTH SS - 6860 UNION VALLEY SS. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Hunt
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ceres BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV 6883 QUINLAN NORTH SS - 6860 UNION VALLEY SS
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW