Basketflower Solar
183 MW generation in Eastland, TX · In queue since October 2024 · Proposed COD December 2027
183 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Basketflower Solar is a proposed 183 MW solar generation project located in Eastland County, Texas. Developed by Basketflower Solar, LLC, the project entered the ERCOT interconnection queue as ERCOT-26INR0468 on October 29, 2024. The proposed commercial operation date is December 31, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV Risingstar (285) - Nimrod (289). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Eastland
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Basketflower Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Risingstar (285) - Nimrod (289)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Basketflower Solar