Little Star Solar
61.6 MW generation in Bastrop, TX · In queue since July 2024 · Proposed COD December 2026
61.6 MW
Capacity
1
Components
Solar
1y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
The Little Star Solar project is a proposed 61.6 MW solar generation facility in Bastrop County, Texas. Developed by RWE Clean Energy Development, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-26INR0511 on July 1, 2024. The proposed commercial operation date is December 31, 2026.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is #9043 CISTERN 345kV. The Little Star Solar project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Bastrop
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RWE Clean Energy Development, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#9043 CISTERN 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Little Star Solar