Jade Flash Storage
320 MW storage in Scurry, TX · In queue since July 2024 · Proposed COD July 2026
320 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-07-01
The Jade Flash Storage project is a proposed 320 MW battery storage project located in Scurry County, Texas. Developed by IP Lumina BESS, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-26INR0516 on July 22, 2024. The current interconnection status is listed as Facility Study, with a proposed commercial operation date of July 1, 2026.
The project consists of 320 MW of battery storage capacity. It is currently listed as active within the ERCOT interconnection queue. The point of interconnection is the 59911 MHOS 345kV location.
Generated from interconnection queue and public data sources
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Lumina BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59911 MHOS 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ANDMDSLR_ALL
- POI Substation
- Mhos Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.