Fagus Solar Park 3 SLF
186.83 MW generation in Childress, TX · In queue since June 2024 · Proposed COD May 2027
186.83 MW
Capacity
1
Components
Solar
1y 11m
In Queue
IA Executed
IA Status
Signed Feb 2019
IA → COD
8y 3m
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-05-19
Fagus Solar Park 3 SLF is a proposed 186.83 MW solar generation project located in Childress County, Texas. The project, developed by Greenalia Solar Power Misae III, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0524, with a queue entry date of June 3, 2024. The proposed commercial operation date is May 19, 2027.
The project's interconnection agreement (IA) has been executed as of February 21, 2019. The point of interconnection (POI) is the 60501 Tesla 345 kV substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Childress
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greenalia Solar Power Misae III, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60501 Tesla 345 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MISAE_GEN_RN
- POI Substation
- Tesla Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Fagus Solar Park 3 SLF