Bypass BESS II
415.97 MW storage in Fort Bend, TX · In queue since November 2024 · Proposed COD April 2027
415.97 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-30
Bypass BESS II is a proposed battery storage project located in Fort Bend County, Texas, with a total capacity of 415.97 MW. The project, developed by Bypass BESS II LLC, is interconnected within the ERCOT region under queue ID ERCOT-26INR0525. The project entered the interconnection queue on November 19, 2024, and has a proposed commercial operation date of April 30, 2027. Its interconnection status is currently in the Facility Study phase.
The development has been mentioned in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
TX
County
Fort Bend
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bypass BESS II LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
44000 Wa Parish 345 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WAP_WAP_G7
- POI Substation
- W. A. Parish Station (345 kV)
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articles