West Munday Wind
351.91 MW generation in Knox, TX · In queue since November 2024 · Proposed COD June 2028
351.91 MW
Capacity
1
Components
Wind
1y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
The West Munday Wind project is a proposed 351.91 MW wind generation facility in Knox County, Texas. Developed by West Munday Wind, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0531, with a queue entry date of November 19, 2024. The proposed commercial operation date is June 30, 2028. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection for the West Munday Wind project is Tap 345kV 60701 Gauss7B _x0013_ 60712 Quasar. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Knox
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
West Munday Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 60701 Gauss7B _x0013_ 60712 Quasar
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.