Jade Thunder Storage
320 MW storage in Scurry, TX · In queue since July 2024 · Proposed COD July 2028
320 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
The Jade Thunder Storage project is a proposed 320 MW battery energy storage system located in Scurry County, Texas. Developed by IP Lumina BESS, LLC, the project entered the ERCOT interconnection queue as ERCOT-26INR0539 on July 22, 2024. It is currently in the Facility Study phase of the interconnection process.
The proposed commercial operation date for the Jade Thunder Storage project is July 1, 2028. The point of interconnection is the 59911 MHOS 345kV substation. The project has appeared in recent news coverage regarding energy storage development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
IP Lumina BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59911 MHOS 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ANDMDSLR_ALL
- POI Substation
- Mhos Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.