Radian Storage IIB (ERCOT-26INR0541) — Project Summary

Queue ID
ERCOT-26INR0541
Capacity
320 MW
Technology
Battery
Status
active
Location
Brown, TX
Region
ERCOT
Developer
IP Radian BESS, LLC
IA Status
Facility Study

Radian Storage IIB

ERCOT-26INR0541BetaActiveBatteryERCOTLBNL

320 MW storage in Brown, TX · In queue since July 2024 · Proposed COD July 2028

320 MW

Capacity

1

Components

Battery

1y 10m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

4 years

Facilities Study50%
Queue EntryJul 30, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-01

About

The Radian Storage IIB project is a proposed 320 MW battery storage project located in Brown County, Texas. Developed by IP Radian BESS, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-26INR0541 on July 30, 2024. The current interconnection status is listed as Facility Study, with a proposed commercial operation date of July 1, 2028.

The project consists of 320 MW of battery storage capacity. It is interconnected at the 1444 Brown Switch 345 kV point of interconnection. The Radian Storage IIB project has appeared in recent news coverage regarding energy storage development in Texas.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Brown

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

IP Radian BESS, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

1444 Brown Switch 345 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.