Three Canes Solar SLF
333 MW generation in Navarro, TX · In queue since July 2024 · Proposed COD July 2027
333 MW
Capacity
1
Components
Solar
1y 10m
In Queue
IA Executed
IA Status
Signed Nov 2024
Queue → IA
4 months
IA → COD
2y 8m
Total Duration
4 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-07-31
The Three Canes Solar SLF project is a proposed 333 MW solar generation facility in Navarro County, Texas. The project, being developed by Three Canes Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0543, with a queue entry date of July 22, 2024.
The project's proposed commercial operation date is July 31, 2027. An Interconnection Agreement (IA) has been executed for the project on November 27, 2024. The Point of Interconnection (POI) is Tap 345kV 3381 Big Brown _x0013_ 68091 Navarro CKT#02.
Generated from interconnection queue and public data sources
State
TX
County
Navarro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Three Canes Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 3381 Big Brown _x0013_ 68091 Navarro CKT#02
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.